CHADDS FORD TOWNSHIP SEWER AUTHORITY
MINUTES
September 17, 2002
The 157th
meeting of the Chadds Ford Township Sewer Authority was held on this
date in the Chadds Ford Township building.
Present: James J. Murray, Chairman, Sandra L. Morgan,
Vice Chairman, Paul G. Linsen, Treasurer, John Spoehr and Jerome S. Heisler,
Jr. Also in attendance were John J.
Mezzanotte, Jr., Esquire, Solicitor, Angelika B. Forndran, P.E., Engineer,
Deborah L. D’Elia, CFT Supervisor and Sabina J. Taylor, Secretary/Treasurer.
The meeting was called to order at 7:00 p.m. by James
Murray, Chairman
ANNOUNCEMENTS:
Chairman Murray reported that on September 10, 2002
members representing the CFTSA and CFT Financial Advisory Committee met with
Michael Wolf, of Dolphin and Bradbury to discuss the ten year cash flow study
and capital investment plan.
PUBLIC COMMENT:
None
MINUTES:
The minutes
of the August 20, 2002 meeting were approved by a majority vote, on a motion
duly made and seconded. Jerome S.
Heisler abstained because he had not read the minutes.
TREASURER’S REPORT:
The
Treasurer’s Report was read. Account
balances were reported as follows:
General
Fund Account
Beginning
Balance $52,530.81
Receipts
26,958.70
Balance $79,489.51
PLGIT/Plus
Account - Tapping Fee Account
Beginning
Balance $441,436.03
Receipts
0.00
Balance $441,436.03
Ridings
Operating Account - First Union
Beginning
Balance $1,000.00
Receipts
.63
Balance $1,000.63
PLGIT
Account - ROA
Beginning
Balance $44,179.28
Transfer
from First Union ROA 0.00
Dividends
for July
60.16
Balance $44,239.44
Disciascio
Escrow Account
Beginning
Balance $15,035.45
Interest
17.76
Balance $15,053.21
Mrs.
Taylor reported on:
1. DVRFA
Interest Payment - An interest
payment of $23,211.25 for this loan is due on October 15, 2002.
2. Driveway
Repair - Mr. Koch has called to say
he is satisfied with the work that was recently done as part of the township road
program. Mr. Kelly had arranged for
improvements to some of the driveway repairs be included in the resurfacing of
Longview Road, and Summit and Woodland Drives.
3. Accounts Receivable -
< 110 Residential and 3 Nonresidential sewer service invoices for the 4th quarter of 2002 were mailed out on September 16, 2002.
< Two more residential tapping fees were collected this afternoon.
< Mr. Krupiak, of CWA, sent a fax on September 16, 2002 stating that the $1,585.36 to cover the cost of repairs to the sewer line caused by CWA will be paid by September 27, 2002.
ACCOUNTS RECEIVABLE:
Chairman
Murray said the issue of property owners that have not responded to the Notice
to Connect must be addressed.
ACCOUNTS
PAYABLE:
Mrs.
Morgan said the invoice from American Water Services includes $135 for
evaluation of the influent pump station for the Ridge Road Project
connection. It should be included in the
General Fund bill list as a Ridge Road Extension Project expense. Corrections
were made to the bill lists, after which, invoices totaling $9,213.41 were
unanimously approved for payment from the General Fund, on a motion duly made
and seconded.
A
motion was made and seconded to approve payment of invoices totaling $6,348.03
from the Ridings Operating Account. The
motion was approved unanimously.
A clarification was requested on several items
listed on the General Fund Balance Details Report as distributed by Mrs.
Taylor. Mrs. Taylor explained that some
of the funds in the General Fund as
shown in the Treasurer’s Report are funds held in escrow against tapping
fees. When these funds are transferred
to the tapping fee account, that does create a deficit in the
General Fund.
This deficit is offset somewhat by General Fund Accounts Receivable in
the amount of $5,721.84. Mrs. Morgan
reminded the members that the Authority is in a negative cash flow
situation.
SOLICITOR’S REPORT:
Mr.
Mezzanotte reported on the following:
1. Thomas Lawrie - At his request, a list of
holders of potential surplus capacity has been provided to Mr. Lawrie. He is present at this meeting to make a brief
presentation regarding property his family owns in Chadds Ford Township and, when
developed, how the sewage from the site may be handled. Mr. Lawrie presented a sketch of a possible
plan and said he would anticipate needing approximately 24 edu of
capacity. This would include service for
the auto dealer and the residential development. Mrs. Morgan told Mr. Lawrie he would have to
contact those with potential surplus capacity to see if he can purchase the
capacity he needs from them.
Mr.
Kelly suggested that it might be best for Mr. Lawrie to start with presenting
plans to the Planning Commission, so that he would have some direction as to
how the site could be developed and then how sewage disposal might be
handled.
2. 19 & 20
Longview Road - The tapping fee for the property at 20
Longview Road is now paid in full.
The
owner of 19 Longview Road has not responded to recent correspondence regarding
the amount outstanding on that tapping fee.
It was suggested that Mr. Mezzanotte should follow up with another
letter to this homeowner.
3. Metro/UTC, Ltd. - Mr. Mezzanotte
said he has been interacting with the contractor to make sure, in closing out
the contract and arranging for final payment, that Metro has satisfied its
contractual obligations. Mr. Mezzanotte
said he understands that the restoration work was performed to the Sewer
Authority’s satisfaction early in September and this afternoon Metro supplied
the paperwork he had requested. Mr.
Mezzanotte said, in his judgement, Metro/UTC, Ltd. is in a position to receive
final payment. Conditions for releasing
the final check were discussed.
4. CCMC & Rullo - The signed
agreement has been received from Mr. Rullo with a check for the tapping
fee. Mr. Mezzanotte said they also
advised him they are making arrangements to convey capacity to two other users
who need to purchase capacity.
Mr.
Mezzanotte has spoken today with the attorney for CCMC who informed him that
his client has the paperwork and he will make a follow up call regarding that
agreement. Mr. Mezzanotte said he
expects to have the agreement and the tapping fee check in short order.
5.Kassab - The Assignment Agreement between Brandywine Summit
Partners and LAPA I, LP. assigning the 22.5 edu of capacity owned by Brandywine
Summit Partners does not contain the language requested by Mr. Mezzanotte. He responded by letter informing them the
original agreement required that future assignments of the capacity were
subject to the written approval of the Sewer Authority. The seller has passed Mr. Mezzanotte’s
letter, regarding the required language, on to the buyer and maybe they will
accept that language. Mr. Mezzanotte
noted he originally said if the language is not incorporated into the
assignment agreement, the Authority will notify the buyer and the township that
the capacity has not been effectively assigned.
6. Delinquent
Nonresidential Account - A formal
notice of intent to file a lien has been sent to the owners of the
property.
Mr.
Mezzanotte explained that, in order to charge attorney’s fees for filing the
lien, the Authority’s fee schedule should include this charge. Mr. Mezzanotte said he would send Chairman
Murray the statutory language requiring this and then something could be
prepared for the other members by the next meeting.
There are a couple of other items from
previous meetings that need to be addressed.
One of these is the Resolution regarding the methodology for setting edu
requirements for nonresidential properties.
Methods being considered are flow calculation based on metered usage or,
to select some reliable source or reference work to set a standard to evaluate
what to allocate to these users.
Chairman Murray suggested that the draft resolution be reviewed and the
members should be prepared to discuss and act on it at next month’s
meeting. Mr. Mezzanotte said he will
send a revised draft, including Mrs. Morgan’s comments, to the Authority
members for their review.
Chairman Murray asked for the status of the
Kids First Agreement. Mr. Mezzanotte
said he has not had any response to the last letter sent from Mrs. Morgan. He said he will call their attorney. Chairman Murray noted at the next billing,
on December 15, 2002, all properties that are part of the BSSE Project will be
billed for service whether they are connected or not.
Mr.
Heisler reminded Mr. Mezzanotte that it was discussed that a resolution needs
to be prepared to provide for an increase in the tapping fee for each
year. It was explained that this
resolution would pertain to tapping fees for existing systems and it would be
adjusted for inflation.
ENGINEERS REPORT:
Mrs.
Morgan reported on:
Ridings WWTP -
1. The printer has been installed, but needs a stand. Jim Murray will get a stand.
2. A new recirculation line for the sand filter is needed. On a motion by Jerome Heisler, seconded by Paul Linsen, the Authority authorized Mrs. Morgan to proceed with having the sand filter recirculation line replaced.
3. New software for the generator at the Woodland Drive pump station has been installed.
The
landscaping at the Woodland Drive pump station needs to be replaced. This will be addressed at another time.
Ms.
Forndran distributed printed copies of her Engineer’s report for this
meeting.
1. St.
Cornelius Holding Tanks - The tanks were pumped out on September 3, 2002 as
planned and no problems were encountered.
It is estimated that they will need to be pumped out two times a week,
with sampling done once a month.
2. Ridge Road
Sanitary Sewer Design -
a. A meeting was held on August 28 with a representative of the Township Engineer to coordinate detour plans and to finalize alignment for extent of sounding for depth of rock.
b. Met on site with Township Engineer on September 13 while Enviroscan was ultrasounding route for rock. Report to be delivered to Township Engineer by September 20 for inclusion in bid package.
c. Resubmitted revised detour plans to Penn DOT on September 10 for Highway Occupancy Permit. The township work on Heyburn road can be sequenced with the sewer work.
d. Met with Conservation District on September 13 to finalize Erosion and Sediment requirements.
e. Preliminary copy of final bid package is being submitted for Sewer Authority review. Permits from DEP, DCCD, and HOP, standard labor wage rates and the Enviroscan report need to be added.
f. The Sewer Authority is only required to advertise for bids once. It is planned to advertise for bids on September 23, 2002 in the Delaware County Daily Times and the Philadelphia Construction News. Notice of Intent to Award Contract will be at the October 15, 2002 CFTSA meeting.
Mr.
Heisler asked if St. Cornelius Church was still interesting in bidding the
project. Chairman Murray explained that
the estimates the church received were considerably higher than the engineers
estimate. Ms. Forndran explained some
changes that are shown on the most recent revised plans for the Ridge Road
Extension Project. She also noted how
these changes will effect the engineers estimate for the project. The plans were displayed and Ms. Forndran
asked if anyone had any concerns or comments regarding the plans, to please let
her know as soon as possible, because the bid documents will have to be ready
by Monday.
Ms.
Forndran said the Authority will work on an Easement Agreement across the
church property to provide for future connections.
Tapping
fee calculations for the Ridge Road Extension Project were discussed.
Mr.
Heisler asked if there were any way to accelerate the project in anticipation
of winter weather conditions. Ms.
Forndran said the way the schedule is now, is very tight.
After
further discussion regarding future connections, A motion was made to authorize
the bid advertisement be published on Monday, September 23, 2002. The motion was seconded and passed
unanimously.
Ms.
Forndran explained that there will be a charge for the bid package and copies
will be available by mail and may be
picked up at Spotts, Stevens and McCoy or at the township building.
OTHER MATTERS:
Tapping Fee Partial Payments - Chairman Murray asked for comments regarding the memo
dated September 4, 2002 relating to this subject. It was agreed that a policy should be set for
handling these extended time payments.
The suggested requirements for qualifying for the extended payment
program were reviewed. The Authority
members agreed in concept with the extended payment plan as proposed.
Mr.
Mezzanotte commented that the Authority might want to consider, as an
alternative to a second mortgage to secure the lien, a municipal lien which
would be a first priority, ahead of any existing mortgage on the property.
ADJOURNMENT:
The
meeting was adjourned at 9:30 p.m.
Respectfully submitted,
Sabina J. Taylor, Secretary