CHADDS FORD TOWNSHIP SEWER AUTHORITY
MINUTES
February 18, 2003
The 162th
meeting of the Chadds Ford Township Sewer Authority was held on this
date in the Chadds Ford Township building.
Present: James J. Murray, Chairman, John Spoehr, Vice
Chairman, Paul Linsen, Secretary, Garry Paul, Treasurer and, Vince Del
Rossi. Also in attendance were John J.
Mezzanotte, Jr., Esquire, Solicitor, Angelika B. Forndran, P.E., Engineer, Jim
Shipley, Chairman CFT BOS and Sabina J. Taylor, Secretary/Treasurer.
The meeting was called to order at 7:00 p.m. by James
Murray, Chairman
INTRODUCTIONS:
Chairman Murray introduced, to those present, the two new
members of the CFTSA, Garry Paul and Vince Del Rossi.
ANNOUNCEMENTS:
On
February 3, 2003 members representing CFTSA and CFT met with their counterparts
in Concord Township to jointly discuss sewer matters in the Route 202
area. This was an information gathering
meeting only and no decisions were made.
PUBLIC COMMENT:
None
MINUTES:
The minutes
of the January 21, 2003 CFTSA meeting were unanimously approved on a motion
duly made and seconded. (Spoehr/Paul)
TREASURER’S REPORT:
The
Treasurer’s Report was read. Account
balances were reported as follows:
General
Fund Account
Beginning
Balance $165,096.19
Receipts
29,500.00
Balance $194,596.19
PLGIT/Plus
Account - Tapping Fee Account
Beginning
Balance $445,001.68
Receipts
0.00
Balance $445,001.68
Ridings
Operating Account - First Union
Beginning
Balance $10,949.34
Receipts 2,627.10
Balance $13,576.44
PLGIT
Account - ROA
Beginning
Balance $54,689.21
Transfer
from First Union ROA 12,576.44
Void
Check #447 700.00
Dividends
52.80
Balance $68,018.45
Disciascio
Escrow Account
Beginning
Balance $15,120.24
Interest
15.06
Balance $15,135.30
Mrs.
Taylor reported on:
1. Budget for 2003 - This budget had been reviewed at the January 21, 2003 meeting but was not formally approved. In response to a question from Mrs. Tobin regarding the amount of money designated for repairs of the plant, Ms. Forndran explained that the amount indicated did not mean that the plant was failing. The amount set aside for replacement and repairs is to cover anticipated normal wear of components of the sewer system. A motion was made and seconded to adopt the Operating Budget and the Capital Budget for 2003 as presented. (Murray/Spoehr) The motion passed unanimously.
1. SSM Invoice for Act 537 Support - This invoice in the amount of $291.72 was presented to the Sewer Authority for approval before being submitted to the Township for payment. The Township has agreed to pay invoices relating to the revisions to the Act 537 Plan which in turn will be 50% reimbursed to the Township by DEP. The Sewer Authority members agreed that this invoice should be approved and passed on to the Township for payment.
3. Terre Hill Proposal - A proposal, dated February 13, 2003, for manhole repairs has been received. The proposal will be discussed under the Engineer’s Report for this meeting.
4. Abbonizio - After review, Chairman Murray signed 4 originals of Payment Request #1.
5. 19 Longview Road Tapping Fee - The members agreed to accept the property owners proposal, dated February 17, 2003, to pay the remainder of the tapping fee in three monthly installments of $200 each.
Chairman
Murray asked Mr. Paul, Mr. Mezzanotte and Mrs. Taylor to work on finalizing the
remaining 5 properties that need to arrange payment terms for paying the
tapping fee.
The question regarding the possibility of using one
checking account was raised once again.
Mrs. Taylor explained the method she uses to keep the Ridings Operating
Account separate from the General Fund Account.
After a brief discussion, it was decided to wait to make a decision on
this until the new members have had some time to review the advantages or
disadvantages of considering this possible change.
ACCOUNTS PAYABLE:
Chairman
Murray asked about an invoice received to review the plans for the proposed
Tremonte subdivision. Mrs. Taylor said
that invoice will be deducted from the $3,000 escrow Tremonte Builders have on
deposit with the Sewer Authority. After
review of the Abbonizio payment request, invoices totaling $184,125.25 were
then approved for payment from the General Fund by a majority vote.
(Spoehr/Paul)
There
being no questions, Ridings Operating Account invoices totaling $10,545.62 were
unanimously approved for payment on a motion duly made and seconded.
(Spoehr/Del Rossi)
ACCOUNTS RECEIVABLE:
The invoice in the amount of $1,219.98 sent to The
Brandywine Conservancy for reviews and inspections relating to the installation
of holding tanks remains unpaid.
SOLICITOR’S REPORT:
Mr.
Mezzanotte reported on the following:
3.
St. Cornelius Church Easement - A proposed
easement agreement has been presented to the church for the easement needed for
Phase 2 of the Ridge Road Sanitary Sewer Extension Project. As requested by Mr. Dunn, solicitor for the
church, Mr. Mezzanotte has revised the description in the latest version of the
agreement. Mr. Dunn will review
the latest revision with the church and will contact Mr. Mezzanotte soon.
4.
LAPA 1 - The executed Capacity Assignment
Agreement has been received.
3. Kids First -The difference between
what the Authority feels is owed and what Kids First feels is owed has been
reduced to about $3,500. Mr. Mezzanotte
has asked the attorney for Kids First to talk with his client to see if some
agreement could be reached so that this matter might be concluded.
4. Brandywine Summit Non-Residential Users -
Mr. Mezzanotte has sent letters
requesting that these three properties be connected within 45 days of the date
of his letter. He said that all three of
the properties have contracted with a plumber to do the work.
ENGINEERS REPORT:
Ms.
Forndran reviewed her written report:
1. RRE - Construction began on January 20, 2003 and substantial completion
occurred by February 14, 2003. All
pipelines have been tested. Some of the
restoration work, such as final paving and seeding, will have to wait for
better weather.
Ms. Forndran noted that, to date, she has received no
written complaints relating to the project.
There was one verbal complaint from a resident on Raven Drive regarding
inconvenience during the construction, and one resident on Ridge Road said the
contractor was very cooperative during this project.
2.
St. Cornelius Elementary School Connection -
Plans were received on February 6, 2003.
SSM review comments were sent out today.
3.
RRSSE Tapping Fee - Cost analyses have
been submitted to Chairman Murray for determination of tapping fee.
4. Inflow and Infiltration - The confined space entry field inspection of manhole 1-26 has been done and it has been determined that it is structurally sound enough to allow proceeding with planned manhole lining to eliminate the inflow and infiltration.
Chairman Murray was asked to sign the purchase order
tonight so that the work on manhole 1-26 may proceed.
5. Ridings WWTP - It has been determined that the location of the sensor for the effluent pump flow meter is causing a biased reading. Possible remedies for this problem, including the installation of a stilling well, were discussed.
The
grease problem at Barnaby’s and the impact of grease on the sewer system
and plant were reviewed. The requirements for grease interceptors are
spelled out in the CFTSA Standards and Details book.
Mr. Taylor, Planning Commission Chairman, said that
the person planning to purchase Barnaby’s had come to the Planning Commission
meeting with sketch plans for the property.
The Planning Commission advised him that there was a grease problem and
a problem with the manhole, and that he should contact the Sewer Authority to
see what needs to be done about these.
Mr. Kelly added that when the plans are reviewed it will be necessary
for the developer to submit his plans to the Sewer Authority for review and
approval before Township approval is effective.
6. Upcoming work - Upcoming items include:
c. Restoration work for Ridge Road sewer construction
d. Storm sewer modification
e. I and I rehab work
f. Review of the draft of the Act 537 plan
g. Scheduling of the inspection of the privately owned sewage treatment plants
Ms. Forndran explained that it has been suggested that
a more detailed engineering inspection be done of the Springhill Farms and
Pantos Wastewater Treatment Plants. She
said this could be done at a cost of between $2,500 and $2,800 for each.
Following further discussion, it was moved and
seconded that Spotts, Stevens and McCoy be authorized to do the engineers
detailed inspection of the Springhill Farms Wastewater Treatment Plant only at
a cost not to exceed $2,800. (Murray/Spoehr) The motion passed unanimously.
The need to adjust the CFTSA fee schedule was
reviewed.
OTHER MATTERS:
Tapping Fee for Ridge Road Sewerage District -
Chairman Murray said that despite the fact that the Authority planned to
announce the tapping fee at this meeting, options relating to Phase 1 and Phase
2 need further review.
After
discussion, it was agreed to recess tonight’s meeting and reconvene on March 4,
2003 at 7:00 p.m. at the Township Building for the purpose of deciding the
tapping fee for the Ridge Road Sanitary Sewer Extension Project. Mrs. Taylor will see that the date for the
reconvened meeting is advertised.
RECESS:
The
meeting was recessed at 10:05.
Respectfully submitted,
Sabina J. Taylor, Secretary