CHADDS FORD TOWNSHIP SEWER AUTHORITY
MINUTES
February 20, 2007
The 208th meeting of the Chadds
Ford Township Sewer Authority was held on this date in the Chadds Ford Township building.
Present: Chairman Vincent Del
Rossi, Vice Chairman Anthony J. Cutrona, Treasurer Keith C. Klaver, Paul Koch.
Not present: Secretary Marc S. Altman.
Also in attendance were J.
Michael Sheridan, Esquire, Authority Solicitor; Thomas R. Smith, PE, Authority
Engineer; Joseph A. Spitko Jr., PE., Asst. Vice President of Spotts Stevens and
McCoy; Joseph Dimatteo, representative of DELCORA Authority Plant Operator; and
Mary J. Walter, asst. secretary/treasurer.
ANNOUNCEMENTS:
- At the February meeting of the
Chadds Ford Township Board of Supervisors, the BOS voted to guarantee the CFTSA
loans that are being applied for the acquisition of the Turners Mill
plant.
- The CFTBOS also submitted an
application for a Safe Water grant in the amount of $250,000.00.
- Today, representatives of the
Sewer Authority Board and the Authority engineer met with officials from
the PA Dept. of Environmental Protection and DELCORA to discuss some
issues with the Ridings Wastewater Treatment Plant.
MINUTES:
The minutes of the January 16
meeting of the Chadds Ford Township Sewer Authority meeting were approved upon
a motion from Mr. Koch and seconded by Mr. Klaver. Approval was granted
contingent upon revision of the minutes to reflect Mr. Klaver’s editorial
changes regarding the PennVest loan. Motion carried.
RIDINGS WASTEWATER TREATMENT
PLANT:
Joseph DiMatteo of DELCORA
reviewed the January operations at the plant. He reported that the sand filter
has been out of service for two weeks and that there were some violations in
February directly related to the poor performance of the sand filter. A
manufacturer’s representative evaluated the filter and made recommendations.
The filter’s being taken out of service and all violations were reported to the
DEP. Mr. DiMatteo expects that the Authority will not be fined because the DEP
okayed taking the sand filter offline; however, the DEP wants the process
expedited. And the manufacturer’s representative guaranteed that the changes
being made will allow the sand filter to meet the criteria for the processing
of waste. Sand filter is being rebuilt and is expected to be online by week’s
end. There will be some violations in February due to the filter being
offline.
Along with the sand filter
problems, the air compressors appear to be “too small” and were running 13 to
15 hours per day. A new compressor is expected to be installed next week at a
cost of $5800.00 per compressor. The old compressor will be maintained as a
spare. Several board members questioned whether the compressors were mis-speced
in the first place when the township engineer and DEP would have had to approve
the installation plans at the time.
Mr. DiMatteo also reported that
there are safety concerns regarding access to the sand filter through the
existing platform and that it must be reconfigured. On a motion from Mr.
Klaver and seconded by Mr. Cutrona, the Board authorized Spotts Stevens and
McCoy to prepare a request for proposal for reconfiguring the sand filter
access platform. Motion carried.
Mr. DiMatteo reported on some
changes in sampling and discharge monitoring procedures that were made based on
recommendations from the Authority Engineer.
At DELCORA’s expense, several
upgrades have been made at the plant to allow equipment to be monitored by
DELCORA’s SCADA system 24 hours per day.
DELCORA received authorization
to make minor mechanical and electrical repairs at the plant. Mr. DelRossi had
been contacted to give approval for minor expenses; the Authority Board will
approve major expenses.
Mr. DelRossi reported that
Hydra-Numatic currently inspects the pump stations quarterly. DELCORA now can
perform the inspections as part of their monthly maintenance. On a motion from
Mr. Cutrona and seconded by Mr. Klaver, the Board voted to approve that DELCORA
conduct the inspections. Motion carried.
DELCORA has submitted a proposal
for televising and evaluating all pipes and manholes in the system to determine
infiltration over a 30-month period. A 6-part plan recommended by the DEP
regarding infiltration and inflow must be included the DELCORA plan, as well as
the corrective action plan and operations manual being developed by SSM. As
well, perhaps the time frame and costs incurred and when should be
re-evaluated. Mr. Koch has some concerns regarding the specifications of the
contract regarding compliance with DEP regulations, certification and qualification
of operators, and a description of what components of the system are to be
evaluated. Mr. Klaver noted that because the proposal was submitted before the
meeting with the DEP, the proposal will be revised to reflect the DEP’s
concerns. On a motion from Mr. Klaver and seconded by Mr. Koch, the Board
authorized Mr. DelRossi to negotiate the DELCORA contract to meet standard
operating procedures and the DEP requirements, after input from the Authority
counsel and engineer in advance of the next board meeting. Motion carried.
ENGINEER’S REPORT:
- CFTSA has authorized SSM to prepare an operations and
maintenance manual for the collection system. Two copies of a draft
manual were prepared and mailed to CFTSA on February 9th for
distribution amongst the authority members, and a separate one was made
for DELCORA. Mr. Smith requested that comments be sent to him within 2
weeks. Mr. Smith was advised that the DEP’s 6-point plan and SSM’s 2004
study should be included as appendices to the report.
- SSM has been revising the electric generator description
for an onsite transfer switch to use with a transportable generator. A
drawing for this equipment has been prepared. This drawing can be provided
to electrical contractors for pricing. Mr. Klaver noted that SSM should
investigate the possibility of leasing a transportable generator on a
continuing basis rather than purchasing one due to cost considerations.
The Turner’s Mill generator is not transportable.
- With DELCORA, SSM is developing the requirements for a
debris basket at the Ridings influent pumping station to protect the
process and sand filter piping from damage due to floatables and
deleterious materials in the incoming wastewater. Mr. Smith stated that
based on the meeting with the DEP, he expects there will be some
requirements regarding sludge holding capacity and equalization tanks.
- The Parkside Associates (shopping mall expansion on NW
corner of Rt. 202 and Ridge Road) sanitary sewer has been installed. A
plug is installed in the line pending testing the lines and manholes. DEP
correspondence has indicted additional work must be done by the developer
on module submittals prior to their acceptance by DEP.
- SSM is preparing the 2006 Chapter 94 Municipal Wasteload
Management Report for your review and comment. In addition SSM is
reviewing the billing rate structure to make the system current with
expected costs. Mr. Klaver noted that the billing re-rate will be focused
on non-residential users. He further noted that the last re-rate review was
completed in 2003 and recommended a rate increase that was not
implemented.
- Turners Mill WWTP is in the final punch list stages of
construction. DEP will be called in for an inspection when the tanks thaw
- they are presently frozen. Estates at Chadds Ford project is completed
and tested. Only record plans remain to be furnished.
SOLICITOR’S REPORT:
- The attorney for Tremonte Builders contacted Mr. Sheridan
to determine what must be done to meet requirements for the dedication of
the system, the maintenance fund and easements. Mr. Sheridan forwarded
boilerplate documents, but has had no response.
- Mr. Sheridan prepared for the Board’s review a
discretionary resolution that allows for the shutoff of water should a
user not pay his/her property’s quarterly user fees. The statute under
which the resolution is enforceable provides due process and protection
for the property owner if the property owner asserts a defense for why the
fees have not been paid. Mr. DelRossi noted that the resolution at present
would not be enforced against anyone. He believes it should be approved to
be used only in rare circumstances. Mr. Klaver introduced and Mr. Koch
seconded a motion that approved the resolution with the caveat that the
approval of the Board must be obtained before the provisions of the
resolution are enforced.
- Mr. Sheridan has contacted PennVest regarding the status
of the Board’s loan application but has had no response. It is expected
that the application will be considered at the PennVest April meeting.
- Mr. Sheridan has begun the process of placing liens on the
RRE2 properties for which full and partial tapping fees are owed.
TREASURER’S REPORT:
- The December financial
statements have been revised to reflect some accruals.
- Tapping fee collections are
being focused upon each individual’s circumstances; several RRE2 residents
have made no effort to respond to the Board or to obtain financing for the
tapping fee. Liens have been placed upon all but one property for which
full tapping fees have not been paid.
- Regarding the January
financial statements, the revenue represents three months revenue while
the expenses represent only one month’s expenditures since fees are billed
in advance. For the first month, costs are in line with the budget to be
proposed for 2007. Mr. Cutrona asked whether the Board is going to meet
with the BOS to discuss the fundamental financial deficiencies the
Authority is facing, specifically in regard to capital costs. Mr. Klaver
noted the meeting has been set for March 7.
- The treasurer’s report and the
accounts payable report including ACH payments for the Verizon and PECO
accounts, debit card expenses, and bill payment list submitted for
approval in the amount of $25254.81 were approved on a motion duly made
and seconded (Cutrona/Koch).
- Mr. Klaver noted that Pennoni
and Associates has been developing 20-year projections that are needed for
the DVRFA loan to be classified as a self-liquidating loan. Because the
loan is self-liquidating the Township’s borrowing capability will not be
affected.
PROPOSED 2007 BUDGET:
- Mr. Klaver noted that the
following assumptions must be made regarding the budget.
- Because of the uncertainty
regarding operating costs at Ridings, as the year unfolds costs could be
higher than they currently are estimated;
- How will Turner’s Mill affect
revenue? It is hoped that Turner’s Mill will generate user fees during
the 6 month period that Toll Bros. will manage the facility. Because of
the uncertainty in timing, Turner’s Mill is not included in the budget.
- Continuation of user rates
for residential and non-residential as of the end of December. Although
additional users are expected, because of timing, additional user fees
and tapping fees are not anticipated.
- There will be no pump and
haul revenue.
- Regarding operating income, it
is consistent with the 2006 operating revenue with the addition of RRE2
customers.
- Regarding expenses, most costs
have been discussed or negotiated; all projections are used as estimates.
There will be a benefit in 2007 of lower interest expense from refinancing
the DVRFA loan to Sovereign.
- The collection system expense
of $32,400.00 is the DELCORA project for televising and examining the
Ridings collection system.
- The monthly DELCORA contract
includes all visits to the plant, unlike the previous contract with
Applied Water.
- Plant maintenance expenses are
budgeted for much less than expended in 2006. Expenses for 2006 were
affected by $15,000.00 to $20,000.00 in unique repair costs for the plant.
This category is also affected by a permit requirement to increase
testing.
- Pump station maintenance
should be lower than last year because all pumps were replaced last year.
- Utility expenses are expected
to be consistent with 2006.
- Mr. Klaver noted that the
Authority is anticipating negative operating cash flow before loan
principal and capital costs are considered.
- The budget assumes $25,000.00
for plant improvements and $50,000.00 for repairs to the collection system
to decrease water infiltration.
Mr. Cutrona questioned where the
unpaid $144,000.00 in tapping fees will be applied to when they are paid. Mr.
Klaver said that the tapping fees will be applied to the investment account to
pay the debt; however, a substantial portion of these receivables are not
budgeted to be collected in 2007. Mr. Cutrona noted that the only place to
which the Authority can look for revenue at present is the users. To finance
the 2007 budget, he projects that there would need to be a $50.00 per month
increase in residential user fees, which he does not believe is reasonable. Mr.
Klaver agreed that he does not see an opportunity for increases in residential
user fees, but believes there is an opportunity to increase non-residential
user fees. The Authority will have to ask for financial help from the Township
for 2007. Mr. Cutrona expressed concern that the projections for capital
improvements and I&I repair costs may not be high enough.
On a motion from Mr. Cutrona and
seconded by Mr. Koch, the 2007 budget was approved.
OLD BUSINESS:
- Mr. Del Rossi noted that the pump
and haul agreement with Toll Bros. has been discontinued and that no waste
is being accepted at the Ridings plant.
NEW BUSINESS:
- At the February BOS meeting,
the Authority requested the Supervisors passed a resolution requiring
notification to the sewer authority regarding sales of homes and allowing
an Authority representative to inspect the home for inappropriate laterals
or sump pump discharge into the sewer system.
- Mr. Klaver requested the Board
authorize Mr. Sheridan to research whether the Authority can charge
tapping fees for new EDUs and how much. Some future EDU holders already
have paid the capacity portion of tapping fees but not the collection
portion of tapping fees.
PUBLIC COMMENT:
ADJOURNMENT The meeting was
adjourned at 10:00 p.m. (Del Rossi/Klaver)
Respectfully submitted,
Mary J. Walter
Asst. Secretary/Treasurer